Class Environmental Assessment Black Ash Creek Sewage Pumping Station Upgrades PHASE 2

Town of Collingwood
Class Environmental Assessment
Black Ash Creek Sewage Pumping Station Upgrades
The Study
Further to the Notice of Study Commencement (issued on January 27, 2017), the Town of Collingwood is continuing to undertake the Municipal Class Environmental Assessment (Schedule B) to consider alternatives to upgrades and improve the Black Ash Creek sewage pumping station include increasing capacity to more than double its current rated capacity. 
The Black Ash Creek sewage pumping station is located on the west side of Balsam Street, north of Black Ash Creek as illustrated on the accompanying map.
The Process
The Town of Collingwood has retained Ainley Group to complete and document a Schedule B Class EA planning process, as outlined by the Municipal Class Environmental Assessment Document, October 2000, as amended in 2015.  
During Phase 2 of the study, alternative solutions were identified and analyzed to find the most appropriate solution for the Town of Collingwood. The recommended solution is the construction of a new sewage pumping station west of the existing sewage pumping station on the same site. Mitigation measures have been developed to minimize, prevent or avoid any adverse environmental impacts. 
How to Get Involved
The Project File, which provides information on the project and the planning process, is being placed on the public record for review and comment. The Report is available for review at the following locations:

Town Hall
97 Hurontario Street,
Collingwood, Ontario

Collingwood Public Library
55 Ste. Marie Street
Collingwood, Ontario

Town of Collingwood Web Site

Mon to Fri: 8:30 a.m. - 4:30 p.m.
Tel: 705-445-1030


Mon to Thurs: 10:00 a.m. - 9:00 p.m.
Fri: 10:00 a.m. - 8:00 p.m.
Sat: 10:00 a.m. - 5:00 p.m. 
Sun: 1:00 p.m. - 4:00 p.m.


Public input and comment on the alternative solutions and recommended solution will be incorporated into the planning process.  Comments received before March 23, 2018 will be taken into consideration in the final stage of Phase 2.
This notice was issued on March 8, 2018.
For further information regarding this project, please contact either of the following members of the study team:
Peggy Slama, P. Eng.
Manager, Environmental Services
Town of Collingwood
43 Stewart Road
Collingwood, ON  L9Y 4M7
Tel:  (705) 445-1581
Fax: (705) 445-0791
Mike Ainley, P. Eng., PMP
Project Manager
Ainley Group
280 Pretty River Parkway
Collingwood, ON   L9Y 4J5
Tel:  (705) 445-3451  
Fax:  (705) 445-0968
Any input received during this process will be maintained on file for use during the project and may be included in project documentation.  Information collected will be used in accordance with the Freedom of Information and Protection of Privacy Act.  With the exception of personal information, all comments will become part of the public record.